Progress of the Project

• Cumulative Financial
• Progress (Nov’15)
• Total: Taka 3240.70 Million (80%)
• GoB: Taka 569.20 Million (42%)
• Project Aid: Taka 2671.50 Million (100%)
• Construction and Equipment installation completed in all 125 UITRCE sites
• Foreign Training completed for 32 officials from MoE, BANBEIS & other allied organizations
• Digital Multimedia Centre established in BANBEIS and operational training completed
• EMIS software integration test completed. Full implementation will be harmonized in second phase UITRCE project.
• Upazila Secondary Education Office activities started and Lab Assistant of BANBEIS posted in UITRCEs
• Local Training of Trainers (ToT) Course completed and 760 trainers has been trained for ICT training of teachers.
• ICT training for teachers in 125 UITRCE expected to be started from Jan’2016. Disbursement of training cost in each UITRCE is under process.
• The Trainers will conduct ICT Training course in UITRCE and about 100,000 teachers will be trained within project period by June, 2017.